Engineering design for Proposed LNG facilities

CARES was appointed to conduct geotechnical investigation for the engineering design for the jetty and LNG loading dock, breakwater and dredged channel.

CARES conducted the investigation and covered the complete geotechnical scope including field data gathering (soil borings for sample collection and cone penetration tests), laboratory testing, data evaluation and preparation of data reports.

The geophysical site investigation included data acquisition utilising Echo Sounder, Side Scan Sonar, Sub¬Bottom Profiler, Magnetometer and, Seismic Refraction.

CARES personnel provided Project Management and Site Supervision Services and the data received was analysed and compiled to form the basis of an interpretive report.

The interpretative report included recommendations for further work, possible pile solutions and dredging designs

Project start: 01 January 2008

Project completion: 31 December 2009

Sector
Infrastructure  Maritime  

Location
Escravos, Nigeria